The passing lanes are nearing completion just east of Kindersley, and Andrew Gulya with the Department of Highways and Infrastructure, said the paving bugun today just east of Kindersley.

"They are working from east end of the paving, which is near the John Deere dealership, and going to the Highway 7 and 21 intersection, and finishing the paving of the passing lanes being put in", Gulya said. 

"This project we are on right now is between Fiske and Kindersley, and we will be putting in a total of 8 passing lanes in, and the construction will going on until at least September", Gulya added.

If you are out and about travelling around the Kindersley area over the next few weeks, expect delays due to paving and passing lanes being put on Highway 7.